United States Tax Court
Petitioner,
v.
COMMISSIONER OF INTERNAL
REVENUE,
Respondent
Date of Decision: June 9,
1966
Judge: Raum.
Tax Analysts
Citation: 1966 CTS 1-93
Principal Code Reference(s):
Section 168 - ACRS Depreciation
Held, an earthslide occurring during the course of excavation
of a building site was a "casualty" within the meaning of section
165(c)(3), I.R.C. 1954. Amount of deductible loss determined.
Full Text
Provided by Tax Analysts. Copyright 2000 Tax Analysts. All rights reserved.
Howard
B. Crittenden, Jr., for the petitioner. Harry M. Asch, for the respondent.
PAGE 302
--
PAGE 303
The Commissioner determined a 7,955.17 deficiency in
petitioner's income tax for 1960. At issue is whether petitioner sustained a
deductible casualty loss by reason of an earthslide, and if so in what amount.
FINDINGS OF FACT
The
stipulated facts together with accompanying exhibits are incorporated herein by
this reference.
Harry
Heyn, a resident of Sausalito, Calif., filed his individual income tax return
for the calendar year 1960 with the district director of internal revenue, San
Francisco, Calif.
Prior
to 1960, Heyn purchased a lot for 18,000 in Sausalito on the corner of Josephine
Street and Atwood Avenue for use as a building site. He owned the property
throughout 1960 and has continued to do so to the present time. The property is
roughly triangular in shape and is a hillside lot sloping in a southerly
direction. It extends 92.42 feet along Atwood Avenue, its northern boundary,
and 64.93 feet along Josephine Street, its southeastern boundary. The property
at its lowest point on Josephine Street is approximately 30 feet lower than at
its highest point on Atwood Avenue.
The
building which was to be erected and which in fact was subsequently erected on
the lot is a two-story structure, consisting of two apartments on the lower
level which have been used for rental purposes and one apartment on the upper
level which has been occupied by petitioner as his personal residence. There
are also carports appurtenant to each level. Petitioner employed a licensed
architect to draw the plans and specifications for the building. Also, licensed
soils engineers as well as structural engineers were hired in connection with
the contemplated construction.
Prior
to any construction contract being entered into, the soils engineers inspected
the property and rendered an opinion on the geologic and soil conditions as
they would affect the support necessary for the building operation. They found
that the basic geologic formation existing on petitioner's property was a
massive fine-grained dense sandstone which was moderately to highly fractured.
Moderately fractured sandstone is fairly unstable, and will not be stable in
excavation cuts having a slope of 55 degrees. If water is present in such soil
there is complete instability. They also found that the lot contained loose
fill. Fill does not have good support or bearing capacity unless it is compact.
Springs are common in the type of geologic formation found on this property.
The architect and structural engineers as well as the parties involved with the
proposed construction
PAGE 303
--
PAGE 304
were
aware of evident indications that water might be present on the property. There
is a visible spring across the street from the property and within 50 yards of
it, which was active and in existence during the years 1959 and 1960. The
structural engineers were concerned about the bearing capacity or stability of
the soil and in particular feared that a spring would impair the stability of a
large portion of the construction site and might cause a slide. Because of the
above problems of the steepness of the hillside lot and the possible reaction of
water on the soil formation found on the property, the soils engineers
recommended that adequate protection be provided during excavation and
construction to prevent movement of the surface soils.
Prior
to entering into the construction contract hereinafter referred to Heyn twice
solicited bids for the construction work to be performed on his property. The
lowest bid in the first set received was in the amount of approximately
105,000. The range of the second set of bids was between 90,000 and 100,000, one
of which included a bid of 17,000 for the foundation.
On
July 16, 1960, the petitioner executed a written contract for the construction
of the structure on his property with the contracting firm of L. E. Weisenburg,
Jr. It was a cost-plus contract with an estimated construction cost of 74,723.
The contractor's fee was 7,659. In some circumstances this fee might be
increased due to changes or it might have been reduced but not below 3,923. The
contractor was to be paid as the job progressed at the rate of 5 percent of the
costs as they were incurred. At that time it was expected that the excavation
of the site would be done by use of a "modified mining technique"
whereby the contractor would excavate narrow trench areas, shore between them
and then build his walls in those areas.
The
agreement stated that the contractor was to "make such shoring during the
course of the excavation and pouring of the concrete as may be required by any
applicable law or ordinance." The applicable law was as follows: UNIFORM
BUILDING CODE 1955 Edition Page 204, Sec. 2801, Excavations:
Any
person making or causing an excavation to be made exceeding twelve feet (12')
in depth below the grade, shall protect the excavation so that the adjoining
soil will not cave in or settle, * * *
The
agreement also stated that "many of the items" making up the total
estimated cost of construction (74,723) were "at the most, educated
guesses or estimates, particularly concerning the excavation and
foundation" and that only when portions of the soil and rock had been
excavated could it be determined whether or not the foundation
PAGE 304
--
PAGE 305
could
be built at an economical price in the manner specified. If it appeared that the
method of excavation was uneconomical Heyn could elect to terminate the
contract.
It
was further provided that the concrete could be poured directly against the
dirt embankment making up the excavation cut in lieu of framing prior to
pouring. This is a type of construction where only one side of the wall into
which one would be pouring concrete is formed. The embankment is the other side
of the form. Time is of the essence in this construction method because of the
necessity that the soil be stable enough to support the vertical cut of the
embankment for a sufficient period of time to permit the concrete to be poured.
It is not possible to pour concrete against a dirt embankment with a T-shaped
foundation. Prior to the execution of the construction contract, the parties
agreed that there would be an L-shaped foundation so that concrete could be
poured directly against the dirt embankment, and the construction contract was
written on that basis.
The
City of Sausalito Building Ordinance No. 508, section 3, provides that whenever
the site covered by a building permit application presents unusual problems in
the opinion of the building official, a foundation plan and site check may be
required. The City of Sausalito building inspector, the building official
referred to in that ordinance, classified the application for a building permit
on the Heyn property as an unusual building problem within the scope of the
ordinance in question. He so classified the Heyn property because of the
anticipated instability of the soil arising from the interaction of the water
on the soil conditions and the steepness of the hillside lot.
About
September 1, 1960, ground was broken at the site. Instead of excavating the
site by use of the "modified mining technique" as previously
outlined, the entire area was excavated, resulting in an exposed vertical
embankment. On September 13, 1960, the engineering geologist employed on behalf
of Heyn inspected the construction site and in particular the vertical cut
slopes of the excavation. At that time, the cut was from 14 feet to 16 feet in
depth. He observed water slowly seeping through "openings in the northwest
corner just above and at the bottom of the excavation." There had been no
measurable rainfall in, on or around the city of Sausalito, Calif., during the
months of June, July, August, and September, all of 1960, so that the water
seepage could not have been caused by excessive rainfall. The engineering
geologist was of the opinion that the cut slopes could not be expected to be stable
for more than a few days without shoring. He called this to the attention of
the contractor by telephone on September 14, 1960, and that conversation was
confirmed by letter the following day.
On
September 21, 1960, the engineering geologist again examined the excavation
together with a representative of the contractor. Two
PAGE 305
--
PAGE 306
4
by 6 support timbers, about 8 feet apart, which had been placed against the
vertical cut by the contractor the previous day were bowed under the load and a
slide seemed imminent. The shoring was inadequate and the engineering geologist
advised the contractor to increase the shoring. The record does not disclose
that such advice was followed.
By
September 22, 1960, the rough excavation was substantially completed. It
resulted in an exposed vertical or 90-degree cut, generally running along
Atwood Avenue. The cut at its greatest depth was approximately 20 feet deep
measured from the existing ground level down to the floor level of the lower
carport. The cut sloped from a maximum of approximately 20 feet to a minimum of
approximately 10 feet.
At
approximately 4 o'clock in the morning, on September 23, 1960, an earthslide
occurred at the construction site which affected a portion of the embankment
from the northerly side of the excavation including the vertical cut, at or
about the point of the deepest excavation and on both sides of the corner.
Approximately 200 cubic yards of earth fell as a result of the earthslide. This
earth came from the vertical embankment and fell into the bottom of the
excavation site.
The
cause of the earthslide was the extensive excavation which produced a 20-foot
vertical embankment by removing the support provided by the portion of the hill
that was cut away, coupled with the failure of the contractor to provide
adequate substitute support with proper shoring. The need for such shoring was
pointed out to the contractor or his employees on several occasions by the
architect and engineers.
At the
time of the September 23, 1960, earthslide construction had proceeded to the
point of a rough excavation. No part of the building had been built. Only a
small part of the framing or forming preparatory to the pouring of concrete had
been erected, and some steel had been put in place. No concrete for the
foundation had been poured and no part of the foundation had been erected.
Because
of the slide, the City of Sausalito closed Atwood Avenue to traffic. Had Heyn
decided to discontinue construction after the slide it appears that he might
still have been required by law to provide adequate support for the roadway and
the adjoining properties. However, the construction of the building was
completed, and it was built substantially according to the architect's plans
and specifications as finally drawn prior to the start of construction. The
cost of the completed building was in excess of 100,000.
In
connection with the construction Heyn expended a total of 36,066.98 for the
completed foundation including concrete and steel. However, it was not
established how much was incurred as construction costs prior to the slide that
took place on September 23, 1960.
PAGE 306
--
PAGE 307
In
his 1960 return Heyn claimed a 16,456 deduction as a "Casualty Loss -- Landslide."
The Commissioner disallowed the deduction in full.
As
a result of the slide petitioner sustained a deductible casualty loss in the
amount of 7,500 that was proximately related to such slide. The remaining
portion of the 36,066.98 expended for the completed foundation represented
petitioner's capital cost thereof and was not attributable to any casualty
loss.
Subsequent
to construction of the building there was litigation between petitioner and the
contractor concerning amounts due to the contractor. Petitioner filed a
cross-complaint for failure to provide the necessary support during the
excavation. The court rendered a written decision but had not yet made any
findings of fact or entered any judgment in that case as of the time of the hearing
in the present case. In that decision Heyn was denied any remedy for breach of
contract or any damages in connection with the slide.
OPINION
Petitioner
seeks to sustain his claimed deduction of 16,456 only as a "casualty"
loss under section 165(c)(3) of the 1954 Code. /1/ Two issues have been
presented for decision: (1) Whether there was a "casualty" within the
meaning of the statute, and (2) if there was a "casualty," whether
petitioner sustained a loss in the amount claimed. We hold that the earthslide
was a casualty within the meaning of section 165(c)(3), but that petitioner has
failed to establish that he sustained a loss in the amount of 16,456, as
claimed. We have found that his loss proximately attributable to the slide was
7,500, and that the remaining portion of the 36,066.98 expended by him for the
completed foundation represented his cost thereof, a nondeductible capital
item.
1.
The Government argues that the landslide was not a "casualty" within
the meaning of section 165(c)(3) because it was merely the product of (a)
anticipated hazards of building on petitioner's property, a steep hillside lot
with an unstable soil condition, and (b) faulty shoring provided by the
contractor. We think that this position takes an unduly narrow view of the
statute.
The
physical characteristics of the landslide were plainly those normally
associated with a casualty. It involved a sudden and violent
PAGE 307
--
PAGE 308
movement
of a large mass of earth that was cataclysmic in character, and was similar in
nature to a fire, storm, or shipwreck. Cf. Ray Durden, 3 T.C. 1; Harry Johnston
Grant, 30 B.T.A. 1028, acq. XIII-2 C.B. 8; Rev. Rul. 57-524, 1957-2 C.B. 141.
But cf. Jones v. Smith, 193 F. 2d 181 (C.A. 10). That it might have been
foreseen or that it might have been prevented by the exercise of due care by
the contractor are factors which in our opinion do not require that the
landslide be denied classification as a casualty.
Of course, foreseeability may be a circumstance to be taken into account in determining whether a particular event is a casualty. But foreseeability alone is not conclusive. Meteorological forecasts may well forewarn a cautious property owner to take protective measures against an oncoming hurricane, but any ensuing losses may nevertheless be storm or casualty losses within the meaning of the law. Nor is negligence a decisive factor. Automobile accidents are perhaps the most familiar casualties today. Yet the owner of the damaged vehicle is not deprived of a casualty loss deduction merely because his negligence may have contributed to the mishap. This is made abundantly clear in the Treasury regulations, sec. 1.165-7(a)(3):
(3) Damage to
automobiles. An automobile owned by the taxpayer, whether used for business
purposes or maintained for recreation or pleasure, may be the subject of a
casualty loss, including those losses specifically referred to in subparagraph
(1) of this paragraph. In addition, a casualty loss occurs when an automobile
owned by the taxpayer is damaged and when:
(i) The damage results
from the faulty driving of the taxpayer or other person operating the
automobile but is not due to the willful act or willful negligence of the
taxpayer or of one acting in his behalf, or
(ii) The
damage results from the faulty driving of the operator of the vehicle with
which the automobile of the taxpayer collides.
We
are unable to perceive any distinction between a casualty loss arising from an
automobile collision and one resulting from a landslide. Certainly, in the
absence of gross negligence, the mere fact that the automobile owner
negligently failed to have faulty brake linings replaced or that he negligently
took a calculated risk in driving with smooth tires would not deprive him of a
casualty loss if his vehicle were damaged in an accident occurring as a result
of either of those conditions. The accident would nonetheless qualify as a
casualty, notwithstanding the owner's negligence or that the accident was the
consequence of his having taken a calculated risk in respect of known hazards.
And it seems clear to us that petitioner's position in respect of the landslide
is no weaker. Indeed, the record does not even reveal any negligence on petitioner's
part. To the contrary, the evidence indicates that the architect and engineers,
acting on his behalf, were urging the contractor to take proper protective
measures that might well have prevented the landslide. We hold that the slide
was a casualty within the meaning of the Code.
PAGE 308
--
PAGE 309
There
are numerous cases involving casualty losses, some of them difficult to
reconcile with others either in result, theory, or language. We think a review
of these cases would not serve any useful purpose here, since we are satisfied
that on the facts before us there was plainly a casualty. Of course, to the
extent that any element of the claimed loss represents merely an increased cost
of the building it is a capital item that is not deductible as a casualty loss.
But that relates to the amount that petitioner is entitled to deduct, a matter
which we consider below.
2.
Although we are satisfied that the landslide was a casualty, petitioner has
failed to carry his burden of proving that he sustained a loss in the amount of
16,456 as a result thereof. That figure appears to be based upon the difference
between (a) petitioner's actual cost of the foundation and excavation and (b)
the aggregate of items of estimated cost of the foundation and excavation as
they appeared in a schedule attached to the original construction contract.
Petitioner makes the wholly unfounded assumption that such difference
represents damages or loss caused by the slide.
It
must be remembered that the contract itself explicitly called attention to the
fact that the estimates in the attached schedule were "at the most,
educated guesses or estimates, particularly concerning the excavation and
foundation." Also, it appears likely that the slide, to a certain extent at
least, merely revealed more clearly or emphasized the need for costlier
construction than had previously been anticipated. Such additional elements of
cost would represent nondeductible capital items rather than a casualty loss.
Similarly, there is some indication in the evidence that local authorities
tightened up some of their requirements or conditions in respect of
construction after the slide. These, too, could represent increased capital
outlays rather than casualty losses. The burden of proof in respect of this
issue was upon petitioner and it has not been carried as to the full amount of
the deduction claimed.
There
is in evidence a mass of vouchers and receipted bills showing petitioner's
expenditures in respect of the foundation and excavation. But it is impossible
to make any accurate allocation between those expenditures that reflected the
loss arising out of the casualty and those that represented merely the cost of
the excavation and foundation. Nevertheless, it is clear that petitioner
sustained some loss as a direct result of the casualty. Thus, the evidence
indicates that, as a direct consequence of the slide, increased labor costs as
well as expenses for lumber and possibly other materials were incurred.
Similarly, the cost of removing the earth involved in the slide and of
replacing some of that material with suitable fill in order to provide the
necessary support for the road on Atwood Avenue may fairly be regarded as
elements of damage proximately resulting from the slide. It seems
PAGE 309
--
likely
that there may have been other costs that could also be directly attributed to
the slide and not be regarded as part of the cost of the excavation and
foundation. As already indicated, the matter is not susceptible of precise
determination on this record, but, doing the best we can with the materials
before us we have found that petitioner sustained a deductible casualty loss of
7,500 /2/ that was proximately related to the slide. Cf. Cohan v. Commissioner,
39 F. 2d 540, 544 (C.A. 2); Austin Clapp, 36 T.C. 905, 908, affirmed 321 F. 2d
12 (C.A. 9); Murray Thompson, 21 T.C. 448, 451, affirmed 222 F. 2d 893, 895
(C.A. 3); David J. Pleason, 22 T.C. 361, 371, affirmed 226 F. 2d 732, 734 (C.A.
7), certiorari denied 350 U.S. 1006; Michael Potson, 22 T.C. 912, 929, affirmed
sub nom. Bodoglau v. Commissioner, 230 F. 2d 336, 341 (C.A. 7); Pauline W. Ach,
42 T.C. 114, 126-127, affirmed 358 F.2d 342 (C.A. 6).
Decision
will be entered under Rule 50.
Footnotes
/1/
SEC. 165. LOSSES.
(a)
General Rule. -- There shall be allowed as a deduction any loss sustained
during the taxable year and not compensated for by insurance or otherwise. * *
* *
(c)
Limitation on Losses of Individuals. -- In the case of an individual, the
deduction under subsection (a) shall be limited to -- * * * *
(3) losses of property not connected with a trade or business, if such losses arise from fire, storm, shipwreck, or other casualty, or from theft. * * *
/2/ We recognize, of course, that the loss is measured by the difference between fair market values immediately before and after the casualty, which, however, may be established by showing the cost of repairs necessary to restore the property to its prior state, subject to the conditions set forth in Income Tax Regs., sec. 1.165-7(a)(2), and subject to the further condition that the loss may not exceed the adjusted basis of the property, sec. 1.165-7(b)(1).